Schedule a production order with operations and job scheduling

网络文摘 William 2035浏览 0评论

Sub-task: Create a production order.
1. Go to Production control > Production orders > All production orders.
2. Click New production order.
3. In the Item number field, enter or select a value.
Select Item number D0001.
4. Click Create.
Sub-task: Schedule operations for the production order.
1. In the list, mark the selected row.
Select the production order that you have just created. It should be at the top of the list.
2. On the Action Pane, click Schedule.
Click Schedule operations.
3. In the Scheduling direction field, select ‘Forward from scheduling date’.
4. In the Scheduling date field, enter a date.
Select a future date, for example, today plus one week. With the selected Scheduling direction, the production order will be scheduled forward from this date.
5. Click OK.
6. In the list, mark the selected row.
7. Note that the status is changed to Scheduled.
8. In the list, click the link in the selected row.
9. On the Action Pane, click Production orders.
Click All jobs.
10. Note that no jobs are created with operations scheduling.
11. Close the page.
Sub-task: Schedule jobs for the production order.
1. On the Action Pane, click Schedule.
2. Click Schedule jobs.
3. In the Scheduling direction field, select ‘Forward from scheduling date’.
4. In the Scheduling date field, enter a date.
Select a date in the future, for example, today plus one week. With the selected Scheduling direction, the production order will be scheduled forward from this date.
5. Click OK.
6. On the Action Pane, click Production order.
7. Click All jobs.
8. Note that based on the active route, 5 jobs are created with job scheduling.